Mansa (ZAMBIA) 16/03/2015. Extension of the School Building. Six weeks after the beginning of the School Extension, the construction works show great progress. The foundations and footing were completed as scheduled. The slab and shuttering was completed on the 5th week. The sixth week shows the actual structrure: classrooms, toilets and corridors slowly began to take shape.